The Grove GTK1100 telescopic tower crane, unveiled at Bauma, has completed its inaugural lift at a jobsite in Germany, following an extensive test programme at the manufacturers Wilhelmshavenplant.
The first unit was delivered in the past few weeks to Wiesbauer, the Bietigheim-Bissingen based crane rental company that helped develop the GTK.
The GTK1100's first job was in Ilshofen, Baden Würtemberg, southern Germanywhere it was used to install a 2KW wind turbine in a field for Repower Systems. The crane is designed to travel on four or five trailers depending on its configuration and local road regulations. The Ilshofen job did not require additional counterweight so its was delivered on four trailers.
The Outriggers are lifted into place:
The hook block is reeved:
The superstructure is raised:
...swung around:
...and lowered into place:
Up goes the mast:
..and locks into the vertical:
The pendant supports are lifted into place:
The pendants are tensioned and the crane is ready to work:
The contract was completed with five lifts, the first three being the tower mast sections that weighed 62 tonnes, 53 tonnes and 45 tonnes respectively.
The second tower section weighing 53 tonnes is lifted into place:
The top section weighing 45 tonnes is located:
The nacelle was next, weighing 70 tonnes followed by the preassembled three blade propeller module. Each blade weighs 8 tonnes with the assembled module being 42 tonnes:
The 70 tonne nacelle, the heaviest single load, is lifted:
The Grove GTK 1100 lifts an eight tonne blade in tandem with a mobile crane, assembling the propeller module on the ground:
The blade and hub assembly weighing 42 tonnes is lifted into place: